Work Procedure

This is the common work procedure and work progress for oil and gas projects. Mostly for conceptual design, FEED and Detailed Design.
  • Start           - (10 %)
  • DDC          - (20 %)
  • IDC           - (30 %)
  • IFC            - (60 %)
  • Re-IFC       - (60 %)
  • AFB/AFC   - (90 %)
  • Final          - (100 %)
This is for reference purposes only, the percentage may differ according to clients and projects.
 
Work Flow
  1. Originator - Generate Reports, Specification, Data sheet, Calculation Sheet and ......
  2.                -  Perform self check of the document above.
  3. Checker/Engineers/Sr.Engineer/Lead Engineer  - Check the document and comment it.
  4. Lead Engineer - Check the document and comment it
  5. Back to Originator - Issue for IDC

Abbreviations:-
  • DDC - Department Document/Drawing Check
  • IDC  - Inter Discipline Check
  • IFC  - Issued for Comment
  • IFR  - Issued for Review
  • IFE  - Issued for Engineering
  • IFB  - Issued for Bid
  • ITB - Invitation to Bid
  • AFC - Approve for Construction
  • AFD - Approve for Design